Smooth Construction Process Enables Early Handover For ALDI Glenelg North
With an eye-catching feature tower, ALDI Glenelg North is capturing attention on the busy intersection of ANZAC Highway and Old Tapleys Hill Rd. The store is ALDI’s 41st location in South Australia, the third to open in 2021 and continues Sarah’s ongoing relationship with the ALDI Group.
Sarah Constructions was engaged on a fixed price contract to complete the build and fitout for the 2000m² site. Scope included construction of an undercroft carpark and feature tower, clad in perforated aluminium with structural steel frame, as well as a ramped walkway, also wrapped in perforated aluminum.
With quick turnaround as a high priority, this project is an excellent example of Sarah Constructions’ ability to program, troubleshoot and communicate effectively to exceed program requirements and deliver handover 2 weeks ahead of schedule.